2nd main line Munich

The 2nd main line represents a significant expansion of the existing S-Bahn system and involves the construction of three additional tunnel tubes, each approximately 7 kilometres long, beneath the Munich city centre.

Large-scale dewatering

The tunnels largely run parallel to the existing main line, creating an important connection between Munich’s main station (Hauptbahnhof) and east station (Ostbahnhof). The goal of this project is to alleviate the existing S-Bahn lines and improve public transport in Munich. The implementation of this project presents several unique challenges, including construction beneath existing long-distance rail lines, U-Bahn lines, and in close proximity to important structures such as Munich’s main station and historic landmarks like the Frauenkirche in the city centre. To ensure our project partners stay dry during construction, we rely on extensive dewatering measures in challenging geological conditions.

Services and technologies

Challenging Dewatering

To protect infrastructure and ensure a dry excavation pit, we planned extensive dewatering measures. This includes approximately 6 km of pressure pipelines, 170 groundwater lowering wells, and 18 infiltration wells.

(Photo: DB Netz AG, panterra.tv)

Groundwater treatment

Additionally, we operate four treatment plants with settling basins for sediment separation and pH neutralisation to clean surface, shift, and groundwater from open dewatering operations.

Monitoring

To control and adjust dewatering if necessary, we have installed a comprehensive groundwater management and process system. This system includes approximately 150 monitoring points connected to a real-time monitoring system.

Project Key Figures

170
groundwater lowering wells constructed.
18
infiltration wells reinfiltrate the groundwater.
10
The 2nd main line is approximately 10 kilometres in total.
150
monitoring points with real-time monitoring.
4
water treatment plants with settling basins and pH neutralisation to clean the groundwater.
430
Groundwater infiltration system with a throughput of up to 430 m³/h.
840
thousand passengers use the Munich S-Bahn daily.